Construction Activities – 6/14/21 – 6/18/21

  • Monday June 14th: T-Bone Construction will start to strip the top soil of vegetation & define the road along the Main Drive on the project site.
  • Tuesday June 15th: T-Bone Construction will be Leveling out the road; this includes removing soil where the elevations are to high & adding soil where elevations are too low. A Water truck will be on site to help with compaction of the soil during this process. Black Hills Gas will also be on site to flag the gas line service.
  • Wednesday June 16th: Activities from Monday and Tuesday will most likely flow into Wednesday & Thursday if they are not completed.
  • Thursday June 17th: Polaris Surveying will be on site to Survey the Retaining Wall on the North end of the project. Polaris is scheduled for Wednesday or Thursday.
  • Friday June 18th: any activities that have not been completed throughout the week will overflow into Friday. I will update this blog with more updates and information as I receive it!
  • Have a wonderful weekend, Be Safe, and stay cool, its going to be a warm one!