Construction Activities – 6/21/21 – 6/25/21

  • After an eventful weekend of Groundbreaking, Spiritual Celebrations & Prayer, Kahn Construction is excited to be moving into this week! Listed below are the actives that will be occurring!
  • Tuesday June 22nd – T – Bone Construction will continue to be working further on Vegetation Removal in preparation to layout & survey the lot structures. In addition to this, T-Bone will also continue to move soil around the site to level out areas where more soil is required & where soil must be removed. These activities will most likely carry into Wednesday, Thursday, & Friday of this week.
  • Wednesday June 23rd – Polaris Surveying will be on site to Survey the South Lot structures.
  • Friday June 25th – Kahn Construction will hold a coordination meeting on site with our Utilities Contractors in preparation to start the Underground Utility work.
  • As always, have a Safe & Wonderful week filled Peace & Care!