Month: October 2023

Construction Activities 10/30/23-11/3/23

The driveways to the houses have been poured. We are working on getting the Communcation lines installed to the houses. We are still working on the mechanical, electrical and the plumbing in the interior of the homes. We will continue to push through the winter to complete the houses.

Read more

Construction Activities 10/23/23 – 10/27/23

Very exciting this week, driveways are going to start getting asphalt. We are in the process of getting inspections for the interior homes. Electrical, plumbing, and mechanical are still in the process. The houses are looking awesome!

Read more

Construction Activities 10/16/23-10/20/23

Construction of the homes is moving along well. We are working on the interior electrical, plumbing and mechanical. Gas lines are being installed to service the houses and same with the electrical services. We are trying to have driveways installed by the end of the month. Please keep safe when you are walking by the