Month: January 2024

Construction Activities 1/22/24-1/26/24

I hope that everyone was able to get through the arctic freeze with no major problems. This week we will have some testing done on the mechanical system in some houses. The interior electrical, and plumbing are almost completed. We are working on the last lots 22 and 23. Interior drywall will continue on the

Read more

Construction Activities 1/15/24-1/19/24

The houses are looking great. We are continuing with installing the drywall in the interior of the homes. Outside finishes are coming along. Mechanical, electrical, and plumbing are still being done inside the houses. Stay warm this week.

Read more