Construction Activities 6/4/21-6/7/21

  • T-Bone Construction will be Mobilizing to the Site This afternoon & evening (6/4/21) as well as Saturday (6/5/21) this includes Mobilizing Equipment & a Jobsite Trailer
  • Pikes Peak Forestry will be preforming work through today & this weekend
  • T-Bone will be Mobilizing The skid, loader, and Conex Next Monday/Tuesday
  • Tuesday the erosion control sub will install silt fence, and we will install the tracking pads
  • Wednesday we will start stripping the site after the meeting with the country erosion control inspector
  • Thursday/ Friday we start cut filling the site to get the road established.
  • Please be safe and have a wonderful weekend to all!