Construction Activities 6/4/21-6/7/21
- T-Bone Construction will be Mobilizing to the Site This afternoon & evening (6/4/21) as well as Saturday (6/5/21) this includes Mobilizing Equipment & a Jobsite Trailer
- Pikes Peak Forestry will be preforming work through today & this weekend
- T-Bone will be Mobilizing The skid, loader, and Conex Next Monday/Tuesday
- Tuesday the erosion control sub will install silt fence, and we will install the tracking pads
- Wednesday we will start stripping the site after the meeting with the country erosion control inspector
- Thursday/ Friday we start cut filling the site to get the road established.
- Please be safe and have a wonderful weekend to all!