Construction Activities: 11.07.2022 – 11.11-2022
- Continue grading and compaction of base course along roadway shoulder
- T-Bone will continue to spread the topsoil
- Minimal construction traffic with the delivery of the stone for the retaining wall
- Kaiser Jones will be installing the retaining wall mid-end of week – weather permitting
- Begin framing the Mailbox Kiosk
Have a safe and relaxing weekend.